Palmet History

Palmet Engineering and Contracting Services Some References

2016

  • Credit Registration Legal Office of Turkey (KKB AOSB – Sincan Data Center) -1st Phase
    • Uptime Institute Tier-IV Certification
    • 44.000 m2 Land (3 Phase), 21.000 m2 Closed Space, Total White Space 4 x 650 m2
    • 2x8 MW Power
    • Dynamic UPS System
    • Air to Air Conditioning
    • Construction - Civil & Architectural Works
    • Power / Energy / Electrical / Mechanical Works
    • Data Cabling / Commisioning
    • Network Monitoring Systems (SCADA, BMS, DCS Systems)
    • Data Center Commisioning / System Transfer
  • Istanbul Metropolitan Municipality – Data Center 1
    • Uptime Institute Tier-III (Concurrently Maintainable) certified
    • 3400 m² Project Space, 2 x 500 m² White Space & Service Hall, 750 m² Technical Space
    • 1750 m² Data Center Management Space
    • 2x1 MW Power,
    • Civil Works / Refurbishment Works / Strengthing Works / Architectural Works
    • Power / Energy / Electrical / Mechanical Works
    • Data Cabling / Commisioning
    • Network Monitoring Systems
    • Data Center Commisioning / System transfer

2015

  • Vakıfbank Umraniye Data Center
    • 900 m2 Project Space, 400 m² White Space, 500 m² Technical Space
    • Uptime Institute Tier-III Certification
    • Construction - Civil & Architectural Works
    • Power / Energy / Electrical / Mechanical Works
    • Data Cabling(Intelligent Patching) / Commisioning
    • Network Monitoring Systems (SCADA, BMS, DCS Systems)
    • Data Center Commisioning / System transfer
  • GEA Klima San. Ve Tic. A.Ş. – Factory Turnkey Operation
  • Hayat Kimya Fire Fighting Systems
    • Hayat Kimya - Nigeria Factory
    • Hayat Kimya – Egypt Factory
    • Hayat Kimya – Mersin Factory
    • Hayat Kimya – Bingo Factory HDPE Revisions
    • Hayat Kimya – Golcuk Factory
  • PALGAZ Revision Works

2014

  • DELTA Combined Cycle Power Plant – 2nd Phase (120 million USD investment value)
  • ERIC 285mW 4pcs HES Energy Power Plant (550 million USD investment value)
  • PALGAZ - PALEN Natural Gas Distributing Networks Investments
  • Turkcell Baskent OMC Building Tier – III Data Center
  • Zorlu Holding – Luleburgaz Textile Factory System Room

2013

  • ALES Combined Cycle Power Plant – 62mW (60 million USD investment value)
  • Fire Fighting Systems
    • FIAT Automotive Factory – 8th Mechanical Building
    • Hayat Kimya – Middle East Hygiene Factory & Cellulose Warehouse
  • Close Cotrol Air Conditioning Systems
    • Turk Telekom IPTV System Room

2012

  • DELTA Combined Cycle Power Plant – 1st Phase – 60mW (60 million investment value)
  • PALGAZ - PALEN Natural Gas Distributing Networks(40 million investment value)
  • Data Center
    • Volkswagen Dogus Financial VDF System Room
    • TURKSAT – Ankara
  • Fire Fighting Systems
    • NETAS, Hayat Kimya–Middle Eastern Factory, Hayat Kimya–North Africa Factory, Kcel –Cyprus, Turkcell Ankara 400m2 Datacenter, Hayat Kimya–1500m2 Electrical Rooms, Hayat Kimy –MCC, Tofaş ASRS Building, Altes, Turkcell, TOFAS, Koc System, Turk Telecom System Rooms
  • Close Control Air Conditioning Systems
    • NETAS, Bakuport, Yapikredi Bank, Kcel –Cyprus, Astana Media Center, Digiturk, Turknet System Room, BSS

2011

  • System Control Rooms
    • Turksat, Denizbank, Koc System, Movenpick Building, Sivas-CEDAS, Burs –Uludag Electric, Digiturk
  • Infrastructure Works
    • Yapı Kredi 2500m2 Data Center
  • Fire Fighting Systems
    • Tofaş, Renault, Turk Telecom Mobile-TV, Koc System, Superonline
  • Close Control Air Conditioning Systems
    • Turk Telekom, Astana Medya Center, Grid Telecom, Alarko - Borsypil Airport, Presidency of the Republic, Erciyes Univercity, SGK Head Office, KCell Server Room, Digiturk, Tubitak

2010

  • Data Processing Centers
    • Global Telecommunication Dudullu Data Center, TRT Head Office, Albaraka Turk Bank
  • ING Bank Data Processing Center Construction and Infrastructure Works
  • Vodafone Tuzla MTX Building - 2x4 MW Power
    • 8.000 m2 Land, 5500 m2 Closed Space, Total White Space 1527 m2
    • Construction - Civil & Architectural Works
    • Power / Energy / Electrical / Mechanical Works
    • Data Cabling / Commisioning
    • Network Monitoring Systems (SCADA, BMS, DCS Systems)
    • Data Center Commisioning / System transfer
  • Datacenter Projects
    • Yapı Kredi Bank, Koc System, Albaraka Turk Data Center

2009

  • Data Centers
    • Oyak Renault Otomobile Factory – New Head Office, Turksat, Erikli Waters & Nestle Waters
    • Yapi Kredi Bank, ING Bank, Zirve University, General Directorate of Forestry
    • Istanbul – Basaksehir Main Pop Point(Tellcom), İzmir–Cankaya Main Pop Point(Tellcom)

2008

  • Data Centers
    • Kalkinma Bank, Antalya - 112 Emergency, METU, POLNET
    • Turksat, Sabiha Gokcen Airport Hangar Constructing, Bahcesehir Tellcom, Deniz Bank
    • Turkcell Mersin GSM Santral, Ankara Metropolitan Municipality

2007

  • Palgaz and Palen
    • Awarded Palmet 87 Gas Pressure Reducing Stations and Metering Systems for their Gebze and Erzurum Gas Networks.

2007 Lootah BC Gas

  • Awarded Palmet 18 Metering Stations for Dubai’s Palm Island Development.

2007 Lootah BC Gas

  • Awarded Palmet a City Gate ‘A’ Type RSM Gas Pressure Reducing and Metering Station for Tanzania.

2007 Temsa – Adana

  • Awarded Palmet a huge Fire Protection Project for its New Plant including Water-Based and Foam Extinguishing Systems.

2007 Eczacibaşi – Kanyon Building

  • Palmet is awarded 10.000 m2 of Raised Floor Systems in this prestigious new development.

2006 Renault

  • Palmet wins further Protection System Contracts for the new wing of Renault Bursa Factory, encompassing Reliable Sprinklers and Valves. Renault is Palmet’s oldest customer with contracts stretching back to 1984.

2006 Turkcell

  • Palmet was awarded the Facility Management Contract for over 1000 BTS Telecom Sites in the Marmara Region of Turkey.

2006 Bloomberg

  • Palmet receives a Design Build Contract Award from Bloomberg’s to build its Data Centre in the Istanbul Kanyon Building, encompassing Denco Air Conditioners, Flopal Raised Floors, Hygood FM200, Tracetek Water Detection Systems, VESDA Early Warning Alarm Systems, GEA Perimeter Heaters and Fan Coils.

2006 Bolu Tunnel

  • Palmet is awarded the Fire Protection Contract for the Bolu Tunnel Projects and installs a Ductile Hydrant Line, Pump Sets and Hose Reel Extinguishing Systems.

Palmet Engineering and Contracting Services References (Continued)

2006 Turkcell

  • Palmet continues its long-term relationship with Turkcell and is re-awarded a planned Maintenance and Service Contract to look after the Denco Ai Conditioning and FM200 Fire Systems in all of their regional Switch Rooms (MSC’s).

2006 Türk Telekom

  • Palmet wins its largest ever contract award from Türk Telekom to supply over 600 Denco Close Control Air Conditioning Systems to be installed throughout Turkey.

2005 Havelsan

  • Palmet was awarded a major Data Centre Infrastructure Package for their Ankara Centre encompassing HVAC, Power and Architectural Systems.

2005 Tubitak

  • Palmet was awarded a Business Management Contract for their laboratories in Gebze.

2005 Paktel

  • Signed Phase II Order with Palmet for a further 220 BTS Stations.

2005 Nortel

  • Palmet was awarded a Telecom Tower Supply Contract in Pakistan.

2005 Oytek

  • Palmet was re-awarded its Long-Standing Service and Maintenance Agreement for their Istanbul Head Office.

2005 Citibank

  • Palmet is awarded the Second Phase of the bank’s brand new building in Ümraniye to provide full Infrastructure Services.

2005 Oytek

  • Palmet is awarded a large ‘POP’ Centre ‘IT’ Room Infrastructure Package.

1987 – 2005 Oyak – Renault

  • Mechanical Works (Fire Detection and Extinguishing Systems, Electro-Mechanical Works)

Palmet Engineering and Contracting Services References (Continued)

1995 – 2005 Turkcell -Ericsson

  • Main Switch Centres and Electronic Offices; Construction Works; Suspended Ceilings, Raised Flooring, Partitioning, etc., Electrical Works: Medium and Low voltage, UPS, Transformers, Generators, Building Automation, Mechanical Works: FM200, Close Control A/C Units, HVAC etc.

1996 – 2005 KOC Group (Kocbank/Kocsystem/Kocfinans/Kocalianz/Koc Bryce/Arcelik)

  • Data Centres and System Rooms (Construction Works: Greenfield Sites, Design and Consruction, Foundations, Seismic Works, Suspended Ceilings, Raised Flooring, Partitioning etc., Electrical Works: Lighting, Medium and Low Voltage Systems, UPS, Building Transformers, Generators, Building Automation, Mechanical Works: FM200, Close Control A/C Units, HVAC etc.)

2002 Palmet/Nortel Networks Joint Venture

  • Largest single contract awarded to date for 2000+ BTS Stations, Palmet took responsibility for Site Acquisition, Enginering, Logistics, LOS, Supply of Towers, Shelters and all Accessories, Implementation, Integration and First Line Maintenance.

1999 – 2004 Avea (Aycell + Aria)

  • Main Switching Centres (MSC’s); Construction Works; Suspended Ceilings, Raised Flooring, Partitioning, Security Access etc., Electrical Works: Lighting, Medium and Low Voltage Network, UPS, Building Transformers, Automation, CCTV, Fire Detection, Mechanical Works: FM200, Close Control A/C Units, HVAC, etc.

2004 Citibank

  • Management Building (Refurbishment Work): Conceptual Design; Interior Decoration, Building Modifications, Suspended Ceilings, Raised Flooring, Partitioning, Furniture, Carpets etc., Electrical Works: Lighting, Low, Medium and High Voltage Networks, UPS, Building Transformers, Generators, Building Automation, Mechanical Works: FM200, Close Control A/C Units, HVAC etc.

2004 SSK

  • Management Building (Refurbishment Work): Conceptual Design; Interior Decoration, Building Modifications, Suspended Ceilings, Raised Flooring, Partitioning, Furniture, Carpets etc., Electrical Works: Lighting, Low, Medium and High Voltage Networks, UPS, Building Transformers, Generators, Building Automation, Mechanical Works: FM200, Close Control A/C Units, HVAC etc.

Palmet Engineering and Contracting Services References (Continued)

2004 – 2005 Pakistan Paktel

  • As a result of Palmet’s considerable success in Pakistan, Paktel, a Millicom company and one of the oldest GSM Operators in Pakistan, concluded a contract with Palmet to expand

their existing Network by providing Site Acquisition, Technical Site Surveys, Tower and Shelter Supplies, Construction and Implementation of over 200 ZTE supplied BTS Stations in the Central and Northern Regions of Pakistan. This project was signed in January 2005 and was concluded early in 2006.

1991 – 2004 T.C. Ziraat Bank

  • Data Processing Centres and Electronic Offices; Construction Works; Suspended Ceilings, Raised Flooring, Partitioning etc., Electrical Works: Lighting, Medium and Low Voltage Power Networks, UPS, Transformer Stations, Generators, Building Automation, Mechanical Works: FM200, Close Control A/C Units, HVAC etc.

1999 – 2004 Zorlu Energy (Bursa, Ankara, Gaziantep Power Plants)

  • Full Fire Scope; Design Services to NFPA Standards, Fire Pumps, Wet & Dry Sprinkler Systems, Hydrant Lines, Foam Systems, CO2, FM200 and Fire Detection.

2002 Tubitak-Ume

  • Palmet successfully concluded an order for the Design, Installation and Commissioning of 98 sets of highly specialized Close Tolerance Air Conditioning Systems for Tubitak’s brand new Testing Laboratories. It total, there were 72 Rooms, including EMC Rooms, Standards Centre, Anechoic Chambers, Electronic Test Beds, Seismic Test Facilities and numerous Clean Rooms.

2002 Oytek Building

  • Palmet successfully relocated Oytek from its existing Facility to a purpose-built Centre in Istanbul, the whole move took 6 weeks from the date of order receipt and at no stage did Oytek suffer any downtime.
  • Palmet’s scope was to provide Full Electrical Power Systems including Transformers, Power Distribution Systems, UPS, Generators, Auto Transfer Switching, Security Access, Lighting, Earthing and features included High Security Zones, Penthouse Suites, Restaurants, Call Centres and is one of the largest Technology Data Centres in Turkey.

2002 Unimar Power Plant (Marmara Eregli)

  • Fire Project; Complete replacement of underground Hydrant Systems, including Cryogenic Activity on live main, Replacement Sectioning Valves while System remained live, New Sprinkler System, CO2 Installation.

Palmet Engineering and Contracting Services References (Continued)

1999 – 2002 Turk Telecom Exchange Buildings

  • Revenue Share project 28 Nos. Fixed line Exchanges, Full Package Supply from Greenfield Site including Design, Construction, Engineering, Architecture and Electro-Mechanical package.

2001 Turk Telecom

  • Palmet received one of the largest orders ever placed in the Close Controlled Air Conditioning Industry Worldwide. It was for the Supply, Installation and 2 years of Maintenance Services for 2250 Close Controlled Air Conditioning Systems. They were built in Denco’s UK and newly opened Turkish Manufacturing Centres. They were for Turk Telecom’s Fixed Line Regional Exchanges located throughout Turkey.

1998 PPG – Bursa (Paint Plant)

  • Full Fire Scope; Risk Analysis, Designed to NFPA Standards, Fire Pumps, Sprinkler System, Hydrant Line (Ductile Iron), Foam System and Fire Detection System.

1995 – 1997 T.C. Vakiflar Bank

  • Data Processing Centre and Office Building Construction; Suspended Ceilings, Raised Flooring, Partitioning etc., Electrical Works: Lighting, Medium and Low Voltage, UPS, Building Transformer, Diesel Generator, Building Automation, Mechanical Works: FM200, Close Control A/C Units, HVAC etc.)

1997 Tengiz Oil – Kazakhstan (Chevron-Bechtel)

  • Main Control Centre Works; Design and Construction of the Aktrau Centre including the supply of Chillers, Pumps, Air Handling Units, Ductwork, Raised Flooring, Building Automation and Power Network.